CH3: Disaster Recovery Planning

Introduction: From Business Logic to Technical Reality

In the previous chapter, we focused on the Business Continuity Plan (BCP)—the "Human and Process" side of survival. We learned how to identify Critical Business Functions (CBFs) and determined how long the business could survive without its tools.

Now, we shift our focus to the Disaster Recovery (DR) Plan. If BCP is about keeping the storefront open and the payroll moving, DR is about the "Bits and Bytes." It is the technical engine room where IT professionals work to restore servers, recover lost data, and rebuild networks after a catastrophe. In this chapter, we will explore the technical architectures that make recovery possible, the specific phases of a DR plan, and how to validate that your technical "safety net" actually works.


Learning Objectives

By the end of this chapter, students will be able to:

  • Distinguish between Business Continuity (BC) and Disaster Recovery (DR) roles and responsibilities.
  • Identify the three primary phases of a Disaster Recovery Plan (DRP): Activation, Recovery, and Reconstitution.
  • Compare technical site redundancy models, including Hot, Warm, and Cold sites.
  • Explain the "3-2-1 Rule" for data backups and the importance of immutability.
  • Describe how Cloud Global Infrastructure and Infrastructure as Code (IaC) facilitate rapid disaster recovery.
  • Analyze the various methods for testing and validating a DR plan to ensure organizational resilience.

3.1 DR vs. BC: The Critical Distinction

While often used interchangeably in casual conversation, Disaster Recovery and Business Continuity have distinct roles within the Contingency Planning ecosystem.

  • Business Continuity (BC): Focuses on People and Processes. It answers: How do we keep the department running if the software is gone? This involves manual workarounds, such as using paper forms, or protocols for relocating staff to alternate work locations.
  • Disaster Recovery (DR): Focuses on Technology and Infrastructure. It answers: How do we get the systems back? This involves technical tasks like restoring from backups, failing over to a secondary data center, or rebuilding a cloud environment from code.

3.2 Anatomy of the Disaster Recovery Plan (DRP)

A Disaster Recovery Plan (DRP) is a formal, technical document providing detailed instructions for responding to unplanned incidents that impact hardware, software, or connectivity.

Scenario: The "Titan Bank" Database Failure

To illustrate the DRP, we will use a realistic scenario: Titan Bank, a regional bank, has discovered that their primary SQL database—which handles all ATM transactions—has suffered catastrophic corruption due to a failed hardware controller.

Phase 1: Notification and Activation

This phase begins the moment a potential disaster is detected.

The DR Team

A standard DR team includes specialized roles to ensure a coordinated response:

  • DR Coordinator: Manages the overall execution and communicates with executives.
  • Database Administrator (DBA): Performs the actual data restoration and integrity checks.
  • Network Engineer: Ensures connectivity to the failover site and updates DNS.
  • Security Analyst: Confirms the failure wasn't caused by an active cyberattack (e.g., ransomware).

Example: The Call List (Emergency Contacts)

The Call Tree ensures the right people are notified in the right order.

Role Contact Name Primary Phone Priority
DR Coordinator Sarah Jenkins 555-0101 1
Lead DBA Mike Chen 555-0102 1
Network Lead Alex Rivera 555-0103 2
Infrastructure Vendor StorageCorp Support 1-800-BACKUP 3

Example: Plan Invocation (The Declaration)

A disaster is not "officially" happening until it is Invoked.

Declaration of Disaster: "As of 08:45 AM, following the failure of the primary ATM SQL Cluster and a failed local hardware repair attempt, I, Sarah Jenkins (DR Coordinator), officially invoke the Titan Bank Disaster Recovery Plan. We are moving to failover operations at the 'Warm Site' located in the Northern Data Center."

Phase 2: Recovery Phase

This is the "Execution" phase where technical restoration work occurs to restore temporary operations.

Example: Technical Runbook (SQL Database Restore)

A Runbook is a step-by-step technical guide for a specific system. It must be detailed enough that a qualified engineer can follow it even under extreme stress.

  1. Verify Integrity: Confirm the last "Known-Good" backup from the immutable storage vault.
  2. Provision Infrastructure: Log into the Northern Data Center management console and power on the standby SQL Virtual Machines.
  3. Execute Restore: Initiate the database restore script.
  4. Update DNS: Change the atm.titanbank.internal record to point to the new Northern Data Center IP.
  5. Validation: Perform a test transaction to confirm the database is accepting writes.

Phase 3: Reconstitution Phase

This phase covers the journey back to "Normal".

  • Failback: The process of moving operations back from the temporary DR site to the original primary site.
  • Data Synchronization: Ensuring all data created while in "Recovery Mode" is successfully moved back to the primary systems.
  • De-escalation: Formally closing the incident and releasing the DR team.

3.3 Disaster Recovery Architectures

The 3-2-1 Rule and the WORM Standard

The industry standard for backup reliability is the 3-2-1 Rule:

  1. 3 Copies of Data: The original and two backups.
  2. 2 Different Media: Storage on different hardware (e.g., local server and cloud).
  3. 1 Offsite Copy: Physical or logical separation.

WORM Immutability: The Digital Vault

Modern disaster recovery hinges on WORM (Write Once, Read Many). This is a data storage technology that allows information to be written to a storage device once, but prevents it from being altered or deleted for a set retention period.

Analogy: Think of a standard backup like a whiteboard. You can write your data on it, but an attacker (ransomware) can easily take an eraser and wipe it out or change the message. A WORM backup is like a stone tablet. Once the data is carved into the stone, it cannot be erased or changed. You can look at it as many times as you want, but the "carving" is permanent.

Site Redundancy Concepts

Before choosing a recovery site, an organization must balance the cost of downtime against the cost of infrastructure. Site Redundancy is the practice of maintaining secondary locations that can take over operations if the primary site fails. These are generally categorized by their "readiness" level.

Site Type Description Cost Recovery Speed (RTO)
Hot Site A fully mirrored data center with real-time data synchronization. Very High Seconds to Minutes
Warm Site Hardware is ready, but data must be restored from backup before use. Medium Hours to Days
Cold Site An empty room with power and cooling; everything must be shipped in. Low Days to Weeks

Cloud Global Infrastructure: Regions and Availability Zones

Public Cloud providers have revolutionized DR by offering built-in geographic separation.

  • Regions: Geographical areas (e.g., US-East). Placing a DR site in a different Region protects against massive disasters like hurricanes.
  • Availability Zones (AZs): Isolated data centers within a Region. Designing for "Multi-AZ" deployment ensures that if a single building fails, your application stays online in another AZ.

Infrastructure as Code (IaC) and YAML

In a disaster, manual configuration is too slow. Instead, we use Infrastructure as Code (IaC) to define our entire data center in a text file.

What is YAML?

Most IaC tools use YAML (Yet Another Markup Language). It is a "human-readable" language used for configuration files that relies on indentation to show how data is organized.

Example: AWS CloudFormation (YAML)

The following YAML script tells AWS to create a virtual server (EC2) and a storage bucket (S3) for Titan Bank's backups:

Resources:
  # This section creates a storage bucket for Titan Bank backups
  TitanBackupBucket:
    Type: 'AWS::S3::Bucket'
    Properties:
      BucketName: titan-bank-dr-backups-2025

  # This section creates a virtual server to run the SQL Database
  TitanSQLServer:
    Type: 'AWS::EC2::Instance'
    Properties:
      InstanceType: t3.medium
      ImageId: ami-0abcdef1234567890 # Example ID for a Windows Server
      Tags:
        - Key: Name
          Value: DR-SQL-Server-01

3.4 DR Testing and Validation: The Rigor of Readiness

A Disaster Recovery Plan that exists only on paper is a liability, not an asset. To be effective, the DRP must be subjected to a rigorous testing lifecycle that moves from theoretical discussion to full-scale technical execution.

The Testing Maturity Model

  1. Tabletop Exercise (Discovery): This is a structured walkthrough involving all key stakeholders. The team gathers in a conference room to "play out" a scenario.

    • Goal: Identify logical gaps, outdated contact information, or missing dependencies.
    • Example: During the Titan Bank tabletop, the team realizes the Lead DBA is on vacation, and no one else has the encryption keys for the backup vault. This "failure" on paper prevents a real failure later.
  2. Simulation (Component Testing): Unlike a tabletop, a simulation involves actual technical work, but within a restricted "sandbox" environment.

    • Goal: Verify that specific technical tasks (like a database restore) actually work without impacting production.
    • Example: Mike Chen, the Lead DBA, attempts to restore a 500GB database to a test server to see exactly how many minutes it takes.
  3. Parallel Testing (Synchronization Validation): In this phase, the recovery site is brought fully online and begins receiving data updates from the primary site, but users remain on the primary site.

    • Goal: Ensure that data is synchronizing correctly and that the DR site has enough "horsepower" (CPU/RAM) to handle the load.
  4. Full Cutover (The Ultimate Test): This is the most rigorous test possible. The primary production systems are intentionally shut down, and the entire organization is forced to run from the DR site for a set period.

    • Goal: Prove beyond a doubt that the organization can meet its RTO and RPO targets.

3.5 Critical Dependencies: The "Hidden" Pillars of DR

A recovery plan often fails because engineers focus on the "Big Servers" while ignoring the "Support Infrastructure." In DR planning, we call these Critical Dependencies.

1. Identity Services (The Authentication Barrier)

If your primary data center goes offline, your Active Directory (AD) or Identity Provider (IdP) likely goes with it.

  • The Risk: You restore your SQL database perfectly, but because the AD server is down, no one can log in to access the data.
  • The Solution: Use Break-Glass Accounts. These are local administrator accounts whose credentials are stored in a physical or digital vault (like a safe). They do not require a network connection or MFA to function, allowing engineers to "get in the door" when the identity system is dead.

2. Networking and DNS (The Routing Barrier)

DNS (Domain Name System) is the "phone book" of the internet.

  • The Risk: Titan Bank moves its operations to the Northern Data Center. However, when customers type titanbank.com, the internet still sends them to the "Old" IP address of the flooded main office.
  • The Solution: DR plans must include pre-configured TTL (Time to Live) settings on DNS records to ensure updates propagate across the internet in minutes, not days.

3. Cloud and SaaS Continuity (The Responsibility Barrier)

Some might believe that moving to the Cloud (AWS, Microsoft 365) means they no longer need a DR plan. This is a dangerous misconception called the Shared Responsibility Model.

  • The Risk: Microsoft is responsible for making sure the servers running "Teams" stay on. However, if a Titan Bank employee accidentally (or maliciously) deletes all the bank's files, Microsoft is not responsible for that data loss.
  • The Solution: Organizations must maintain third-party backups of their SaaS data (e.g., backing up Microsoft 365 data to a different cloud provider).

Summary and Key Terms

Disaster Recovery ensures the technology is ready to support the business when normal operations fail. A robust DRP focuses on automation through IaC, immutability through WORM, and rigorous validation through testing.

  • Failover: Switching to a backup or secondary system.
  • Failback: Returning to the primary system after a disaster.
  • IaC (Infrastructure as Code): Managing infrastructure through scripts and code.
  • WORM: Write Once, Read Many; a storage standard for data permanence.
  • Break-Glass Account: Emergency, high-level credentials for use when authentication systems fail.